Work continues on reactive road repairs across Buckinghamshire that resulted from the very wet winter, but with the warmer weather now here, the council’s attention has turned to major planned works on Buckinghamshire roads such as full resurfacing schemes, extensive plane and patch, as well as permanent fixes on bigger road defects.
Summer sees the start of a full range of capital improvement works, with over 320 schemes to be delivered, including larger resurfacing projects, major drainage improvements, footway works and road safety projects on specific sections of the highways.
As part of Buckinghamshire Council’s rolling £110m investment in roads across the county over four years, work is taking place at the following locations through Buckinghamshire Highways' Strategic Highway Maintenance Programme.
The works are part of a programme of countywide work and some activities are extremely weather dependent, therefore dates shown are subject to change at short notice. These dates may also be subject to change depending on the availability of materials and unforeseen circumstances out of our control.
The roadworks scheduled are as follows:
Soulbury Road, Wing Monday July 8 to Tuesday July 16 conventional resurfacing works using a road closure in operation 9:30am to 3:30pm.
Battings Wood Green, Naphill Monday July 15 to Tuesday July 16 conventional resurfacing works using a road closure in operation 8am to 5pm.
Upper Street, Tingewick Tuesday July 16 to Wednesday July 17 conventional resurfacing works using a road closure in operation 8am to 5pm.
Cresswell Road & Appletree Walk, Chesham Tuesday July 16 to Wednesday July 17
conventional resurfacing works using a road closure in operation 8am to 5pm.
Snowhill Cottages, Ashley Green Thursday July 18 to Friday July 19 conventional resurfacing works using a road closure in operation 8am to 5pm.
Penn Avenue & Chapmans Crescent, Chesham Thursday July 18 to Tuesday July 23 conventional resurfacing works using a road closure in operation 8am to 5pm.
Bicester Road, Ludgershall Monday July 15 to Thursday July 18 plane and patch works using a road closure in operation 8pm to 6am.
Hamilton Gardens, Burnham Monday July 15 to Friday July 19 plane and patch works using a road closure in operation 7am to 7pm.
London Road, Aston Clinton Tuesday April 2 to Tuesday August 20 traffic calming works using a combination of both two-way and three-way temporary traffic lights in operation between 8am to 5pm.
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel