This is where Transport for Bucks will be working this week. 

Some work is weather dependent, so some dates may change at the last minute. 

For all other roadworks, see one.network 

Conventional Surfacing Programme

  • Ledborough Lane, Beaconsfield – B474 Penn Road to A355 Amersham Road (Monday 29th  March to Saturday 22nd May). Carriageway reconstruction works using a road closure in operation 24/7

Surface Dressing Programme 

  • Granborough Road, North Marston - Green End to Quainton Road (Monday 29th March to Tuesday 30th  March). Preparatory patching works using a daytime road closure in operation between 7:30am and 6pm
  • Thame Road, Brill – The Old Chapel to the B4011 (Monday 29th March to Wednesday 31st March). Preparatory patching works using a daytime road closure in operation between 7:30am and 4:30pm

Plane and Patch Programme

  • Lodge Lane, Little Chalfont - Burtons Lane to 104 linear metres from Burtons Lane (Wednesday 1st April). Patching works using a daytime road closure in operation between 7:30am and 4:30pm
  • Gold Hill East Service Road, Chalfont St Peter - Gold Hill North to Cherrytree Lane (Monday 29th March to Wednesday 31st March). Patching works using a daytime road closure in operation between 7:30am and 4:30pm
  • Gold Hill, Chalfont St Peter - Gold Hill North to Austenwood Close  Wednesday 31st March to Friday 9th April). Patching works using a night time road closure in operation between 7:30pm and 6am

Footway Structural Repair Programme

  • Desborough Avenue, High Wycombe – Deeds Grove to Kitchener Road (Monday 29th March to Monday 5th April). Footway reconstruction works using footway closures and temporary traffic signals in operation between 9:30am and 4pm
  • Poles Hill, Chesham - Darvell Drive to Chapmans Crescent (Monday 29th March to Thursday 8th April). Footway reconstruction works using localised traffic management in operation between 7.30am and 5pm
  • Poppy Road, Princes Risborough - A4010 Wycombe Road to B4444 Station Road (Monday 29th March to Monday 19th April). Footway reconstruction works using footway closures and temporary traffic signals in operation between 7:30am and 5pm