‘Significant’ changes to the proposed mitigation work planned for Link Road have been agreed – with all but one of the trees by the road remaining untouched.
HS2 representatives met with Bucks County Council councillors and agreed to the changes by reducing the length of the widened section up to the A413 roundabout.
The trees that will be protected include the tree at the turning into the Buryfield recreation area.
Representatives from the council, including leader Martin Tett and cabinet member Mark Shaw, visited the site and protestors who had gathered to campaign against the work.
Developers Fusion will now carry out the necessary detailed design work to incorporate the agreed changes.
Official figures show the number of HS2’s HGV’s using the junctions at Frith Hill and Link Road will result in both becoming heavily congested at peak periods of the day.
Although mitigation work continues at Frith Hill, it is expected that the Link Road work won't now begin on site until late February next year at the earliest, subject to the outcomes from the long-awaited Oakervee report.
Martin Tett said he was very happy that a scheme had now been designed which both provided acceptable traffic mitigation whilst, most importantly, protecting the local environment.
"As someone who has spent ten years fighting HS2, not least the trail of destruction it will cause as it carves its way through the very heart of Buckinghamshire, I am delighted that we seem now to have a scheme which is an acceptable compromise, both protecting our beautiful county, whilst letting people get to and from their work during the many years of construction that potentially lie ahead.
"I had previously written to Grant Shapps, the Secretary of State for Transport, on three occasions and also the Prime Minister asking for the work on HS2 across Bucks to be halted pending the outcome of the Oakervee Review.
The Government would not agree to this; however, the redesign of this mitigation scheme will mean that no work will now take place for almost four months. This should be after the Oakervee Review is published.
I still hope that the Review will see HS2 cancelled, but in case it is not, we need to ensure adequate mitigation for our residents."
"We've listened and we've acted to get the best outcome. I hope we can now all come together in the best interests of everyone in Great Missenden and the surrounding area as we all prepare to cope with the day to day effects of the massive construction about to take place should HS2 go ahead."
Speaking from Westminster, Dame Cheryl Gillan MP said: “Having met with campaigners, councillors and HS2 to try and halt these works until after the Oakervee Report has reported, I am delighted that we have obtained this pause which will alleviate the stress on the village in the run up to Christmas.”
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel